Stress Engineering Services
Search  

Other Stress Websites


Stress Subsea, Inc.

Mohr Engineering

Chemical & Refineries Consumer Products Legal Medical Devices Oil & Gas Pipeline Plastics Power Pharmaceutical

LIFE ASSESSMENT AND EXTENSION

  Request Info
                


    Stress Engineering Services has performed design, analysis, and testing projects for petrochemical plants, fabricators, and manufacturers since 1972. These typically involve design analysis of components, vessels, and piping such as valves, towers, and FCCU plenum chambers. The ANSYS and ABAQUS finite-element programs are typically used  to provide stress results to be compared to allowable Code Stress limits or for fatigue evaluation.


    Fitness for Service Application Examples


    Summarized below are several Fitness-for-Service application examples that were performed by our expert staff. Some of these were completed by the individuals prior to their career at Stress Engineering. This is only a brief list of examples, but they illustrate the unique problems encountered and the solutions developed.


    1.  We analyzed an existing chemical plant piping system and found thermal stresses to be excessive. We recommended that the piping be redesigned for improved flexibility and code compliance. We did the redesign including pressure, thermal, and wind under various configurations.


    2.  A caustic quench pressure vessel with circumferential cracks was reviewed for a chemical plant. We recommended temporary structural repairs and reinforcement to maintain pressure integrity while a new replacement vessel was under construction.


    3.  Numerous pressure vessel re-rates have been performed for heat exchangers and vessels in ethylene service which had not corroded in 15 years. The re-rates took advantage of the validated zero corrosion on vessels that had up to 1/8-inch corrosion allowance.


    4.  A carbon steel vessel with a monel liner had corrosion-under-insulation damage. Extensive corrosion was found which reduced wall thickness below acceptable limits. In fact, some areas were so severely corroded that the carbon steel was completely missing leaving only the monel liner to contain pressure. This vessel was temporarily repaired by using an overlay patch as permitted by API-510. Temper bead welding was used to post-weld heat treat in place of full circumference conventional heat treat. This repair scenario resulted in a minimal shutdown of the unit. Since all the procedures were non-intrusive, there was no cleanup, purging, or contamination of the process.


    5.  An evaluation was performed for an internal catalyst grid support ring using elastic/plastic finite element analysis. The objective was to determine the limit load that could be supported by the ring. This sophisticated means was needed to avoid rebuilding the support structure inside the vessel. This was a classic miscommunication between the support grid manufacturer and the vessel fabricator. Each placed responsibility of the structural adequacy on "others". We assisted in the redesign of internal support clips, which were themselves over-stressed, and performed calculations to justify the stresses imposed on the vessel wall. This work was completed wholly with conventional calculations.


    6.  Cracking of a vessel shell under an internal head was evaluated using finite-element formulation and fracture mechanics techniques to determine critical flaw size and expected life. This project included a 3-D shell/plate element model to determine gross loadings, a 2-D axisymmetric model to determine peak loading, and crack initiation and growth in the area of concern.


    7.  Two fracture related FFS tasks were carried out related to pressure containment structures in a 1500-MW pressurized water nuclear plant. The first was initiated by a non-conformance in welding procedure during the welding of the vertical seams in the steel lining of the secondary containment. These welds were made by a proprietary process similar to electroslag welding, which produced large grain sizes with consequent low Charpy impact values. The question was whether any thermal or mechanical loadings experienced during the remainder of construction (since the lining was the inner staging for casting the concrete walls) or during an in-service transient, could cause a brittle fracture and release of contaminated steam to the environment. The work entailed developing correlations between subsize Charpy impact test results and conventional fracture mechanics parameters, then using these to investigate behavior of the lining under a wide range of loadings, including shrinkage of the concrete, causing inward buckling of the liner, thermal transient due to general and local steam impingement, and mechanical damage due to pipe whip or missiles.


    The second problem was concerned with the discovery in the main nuclear vessel after installation of reheat cracks on the interface between the ferritic wall and stainless-steel lining. Solution of this problem involved both deterministic and probabilistic analysis. The probabilistic analysis was used to develop a statistical description of underclad crack sizes, based on Framatome QC data. The deterministic analysis involved considering all projected thermo-mechanical transients projected (approximately 30 transients) to calculate crack growth using Paris Law type data. Finally, estimates were calculated of the probability of fast fracture being initiated from the growing defects in the event of (for example) a Loss of Cooling Accident.


    8.  An advanced gas reactor power plant was experiencing cracking in attachment welds in the serpentine tube platens used to construct the heat exchangers for their gas-cooled reactors. Since the outside of the tubes is in contact with the primary circuit coolant, through-cracks in these tubes constitutes a beach of the primary containment, with significant safety implications.


    The first part of this work was a probabilistic evaluation of defect sizes and locations, based on NDE and destructive metallurgy carried out on sample attachments. This was followed by development of a methodology of cycle-by-cycle measurement of combined creep and fatigue damage at critical locations. Given the year, this work predates the current practice of using the C* or Ct concepts for creep crack growth analysis, and used instead a method developed from first principles, which turns out to be almost identical to the current C*-based approach. (This project is described in "Design for Creep" by Penny and Marriott, 2nd ed., Chapman Hall, 1995.)

     

    The final stage of the project involved working with NEI to implement an automated PC-based system to track damage on-line in the plant on a cycle-by-cycle basis.


    9.  Matimba Power Station, a power plant in the Northern Transvaal Republic of South Africa, uses a compact design in which superheaters are placed at the top of the boiler, and the preheaters are at ground level. The two components are linked by large ducts, 30" in diameter and more than 300? high, made of a high-phosphorus structural steel for improved creep resistance. Unfortunately, this means that the steel is also susceptible to temper embrittlement.


    After only a few years in service, large cracks were found in the ducts. Charpy tests indicated serious embrittlement. The question was, given the low anticipated service loadings, would the ducts be fit for service in the cracked condition, since the cracks did not materially affect the station?s operation? Stress Engineering?s involvement was to critically examine the operating envelope of the station, and identify thermal loadings not considered by the contractors. Firstly, these were the cause of the observed cracks and, secondly, could lead in the future to a catastrophic collapse of the ducting.

    This work involved developing a model of the temper embrittlement process, as it pertained to degradation of fracture toughness over time, based on work done in the nuclear industry to predict the effects of radiation embrittlement. This model was used to perform a probabilistic evaluation of the risk of fast fracture, from existing cracks, or simply from embrittled material.


    10.  The MPC (Materials Property Council) OMEGA Project is an ongoing industry-sponsored project aimed at developing a reliable and economical means of tracking progress of creep damage in petrochemical plants. It involves both analytical studies and innovative test procedures, whereby the remaining life of a component can be estimated with a minimum number of creep tests and in a minimum of test time.


    Specific involvement by Stress Engineering in this project is to develop a generalization of the simple uniaxial version of the OMEGA approach, to take into account the multi-axial stress states which are encountered in real components. The work includes collection of a database of well documented tests on multi-axial specimens, such as notched bars and tubes under internal pressure, and such testing to rupture on real components such as pressure vessels containing nozzles, to act as a base for validation. The other element of the project is nonlinear structural analysis of these sample problems, using ABAQUS and a British FE program called LUSAS, both of which permit the analyst to use special material constitutive relations to describe creep and creep-damage accumulation.